本帖最后由 webyl 于 2017-3-24 14:32 编辑 # Q) ~4 Q( E% M8 l% h( j
; l$ B+ J i# B X
现在对以前的文章进行补充- 飞机吊装运输马来西亚天空之桥(Langkawi Sky Bridge)从图片到结构推测分析与遐想 LANGKAWI SKY BRIDGE
, g; }& ~0 s5 J& R) D7 E" n2 ]" y/ [Langkawi Sky Bridge is a 125-metre (410 ft) curved pedestrian cable-stayed bridge in Malaysia, completed in 2005.The bridge deck is located 660 metres (2,170 ft) above sea level at the peak of Gunung Mat Chinchang on Pulau Langkawi, the main island of the Langkawi archipelago in Kedah.The Langkawi Sky Bridge can be reached by first taking the Langkawi Cable Car to the top station, where an inclined lift called SkyGlide takes visitors from the top station to the bridge. The bridge was closed in July 2012 for maintenance and upgrading. The reopening was put off several times, but it partially reopened in February 2015.The bridge is now fully accessible.. V5 M/ A. j6 Y, y3 q" a/ q: Y
0 w4 @( r* m' o5 a( n% X" J
Design and layout The bridge is 125 meters long, and 1.8 meters wide (the middle section has a wider walkway), with two steel railings as well as steel wire mesh on either sides. It is designed as a curved walkway to maximise the viewing experience, providing shifting perspective as a visitor walks along the bridge. The walkway, formed of steel and concrete panels set on top of an inverted triangular truss, connects two hilltops at Gunung Mat Chinchang. The first 25m of the bridge is straight, following 3 curved 25m sections, then a final straight 25m section. At each end of the walkway, the bridge has a 3.6m-wide triangular viewing platform that serves as resting and viewing areas for visitors.
" F( N- m) ^! z& v* ]The bridge is suspended by 8 cables from a 81.5m high single pylon, and hangs at about 100m above ground. The pylon is anchored onto a concreted pad set at an elevation of 604.5m, and its tip reached 686m above sea level. It is inclined at angles of 78° and 2° in two directions, and supported by two cables. The bridge is designed to carry a maximum capacity of 200 persons. " T7 t. G% \* u0 r& j
Construction The bridge was pre-fabricated, and sections were then lifted to the top of the mountain using Russian Kamov helicopters, and the entire bridge assembled in its current position by the pylon. Helicopters were used in the erection of the pylons and the main section of the deck, later decks sections however were assembled using more conventional working cable and winch system. The bridge roughly costed $1.2 million dollars to construct.The bridge was constructed in 12 months between August 2003 and August 2004. It was opened to the public on February 2005. - _% {# I) B* e E7 M% e
* V" G( Z$ T2 Z6 Q
) d, H. t5 A9 e6 \( J
0 w `" \; `- `2 P3 [ y+ u7 |
0 v& R+ H( F V
. {: W% C: S8 ]) B& x+ ?
6 {. @( k: w8 \& v
, G" o2 g( S( K' @' h- F" K/ a
4 s; a3 p* u7 c4 {. v5 f6 _
* [/ c; Z3 E4 k0 y! ?. J+ {
! ~- o4 f# [& Y$ I/ Y+ B I3 [* N: P
6 X, G3 J$ {& \( ^" b- N% X7 N# }& T3 A( k
, V1 M l! P' E6 k8 @1 c4 a7 ~7 d
+ Y) t/ K9 k" R7 `( D) R
5 o5 i! j: B1 l0 o
! P" T7 w |* H) d$ E, `7 G5 s: S% k) p- }* h5 @: x, b
, |0 }6 r) k- p
{, G0 _7 Z' W0 _6 K
' ]$ u& E* Q6 S( ]' t% D9 s* v) i/ }& C+ A/ Z
/ m' s5 y5 y; m+ ]/ y
+ [9 T. f. G& ~* u" I( }: c
! q3 @: G1 d7 h+ F0 U$ ~# j6 a2 ~/ H! D! B5 t8 v7 o$ \6 U
|